Major Alternator Overhaul & Crane Recertification at Anchorage

Marine alternator overhaul · engine-room crane recertification24/7 anchorage attendance
Completed

Scope of Work

  • Complete alternator disassembly and extraction of heavy components, including stator casing and rotor handling, with barge support
  • Heavy-lift handling of components weighing approximately 4 tonnes under round-the-clock operations
  • Coil resistance measurements, insulation testing and diagnostic verification of the exciter and alternator windings
  • Mechanical servicing, electrical troubleshooting and control-system inspection of the engine-room service crane
  • Static and dynamic proof-load testing using a calibrated load cell for crane recertification

Project Outcome

Ocean7 Maritime executed the alternator overhaul and crane recertification at anchorage through continuous coordination between the vessel, workshop, barge, rigging and technical teams. The required electrical checks, heavy-lift handling and proof-load testing were completed successfully while keeping vessel downtime to an absolute minimum.

Published: August 2026
Industrial alternator motor with terminal box open during diagnostic testing with a digital multimeter
Coil resistance and insulation testing of alternator components using Fluke and Sanwa multimeters on a workbench
Heavy machinery housing suspended by crane hook during night lifting operations at anchorage
Overhead view of crew guiding a heavy-lift machinery component on the vessel deck at night
Wrapped cylindrical component lifted by crane with a crew member in coveralls overseeing the operation
Pale-green machinery unit suspended above the deck during crane recertification lifting operations
Crane lift of a wrapped cylindrical load with deck machinery during night operations
Euroload telemetry load-cell display showing a calibrated weight reading during crane proof-load testing
Crane lifting wrapped cylindrical machinery on the vessel deck with crew coordinating below

Emergency Anchor & Anchor Chain Replacement

Laden container vessel · approx. 200 m12-hour turnaround
Completed

Scope of Work

  • Emergency anchor and anchor-chain replacement
  • Chain shots laid out, painted and visually inspected, with individual links checked
  • Heavy-duty anchor rigging and hoisting coordinated with support tugs and heavy machinery
  • Anchor positioned and final connections secured into the windlass
  • Hawse-pipe clearance verified and onboard anchor system tested operational

Project Outcome

The complete emergency replacement was carried out within a 12-hour operational window, enabling the vessel to resume its sailing schedule without missing its berth commitment.

12-Hour Mission Timeline

18:00Ground preparation — chain layout, painting and inspection
23:00Heavy rigging and anchor hoisting
04:00Final connection, securing and system testing
07:00Vessel ready to sail
Project partner: Arun Energy Limited and supporting yard team
Published: August 2026
Loaded container vessel alongside a shipyard at sunset during the emergency anchor and chain replacement project
Anchor chain shots laid out ashore for inspection and preparation during night operations
Replacement anchor being hoisted beside the bow of the container vessel with tug support alongside
Container vessel alongside at night during the completed emergency anchor and chain replacement operation

Barge Mobilisation — Jurong Island

Marine mobilisation projectSingapore
Completed

Scope of Work

  • Mobilisation support for a barge project bound for Jurong Island
  • Coordination between operational and technical teams
  • Yard-based preparation and mobilisation activities
  • Marine operations coordination using Arun Group Shipyard facilities and yard support
  • Safe completion of the mobilisation operation

Project Outcome

Ocean7 Maritime supported West Squadron Marine Services Pte Ltd on the recent mobilisation of a barge project heading to Jurong Island, with the operation carried out at Arun Group Shipyard through coordinated yard and marine support.

Project partner: West Squadron Marine Services Pte Ltd · Arun Group Shipyard
Published: July 2026
Flat-deck barge alongside an industrial wharf during mobilisation work for Jurong Island
Crew carrying out deck and mooring operations during the Jurong Island barge mobilisation project

24-Hour Air Cooler Turnaround at Anchorage

Main engine air cooler servicing24-hour turnaround
Completed

Scope of Work

  • Removal of a heavily choked main engine air cooler while the vessel remained at anchorage
  • Hoisting and transfer of the air cooler ashore for servicing
  • Workshop cleaning and servicing of the air cooler core
  • Logistics coordination between vessel, workshop and supporting partners
  • Return transport and lifting of the serviced air cooler back onboard

Project Outcome

Ocean7 Maritime coordinated a one-stop response for a vessel at anchorage experiencing a heavily choked main engine air cooler. The unit was removed, transferred ashore, serviced and returned onboard within approximately 24 hours, minimizing disruption to the vessel's schedule.

Published: April 2026
Air cooler core being handled by forklift during night workshop logistics
Air cooler unit being lifted back onboard a vessel by crane at anchorage
Serviced air cooler packed on a pallet for transport back to the vessel
Air cooler unit suspended in the engine room during reinstallation
Air cooler tube stack being water flushed and checked during workshop servicing
Project descriptions are based on verified public project information. Client, vessel and location details may be withheld where confidentiality or operational considerations apply.